Signing a contract with KGHM Polska Miedź S.A Głogów smelter branch
Subject of the contract: Execution of disassembly and assembly works for the task “TE Installation of diagonal pump 50D22 at PZ and PE HMG pumping station”.
Task scope:
Carry out disassembly and installation work of a multi-discipline nature, including:
- Installation of power and control of the pumping unit with integration into the HMG Superior Control System.
- Preparation of the stand for the installation of the diagonal pump
- Integration and installation of Powen diagonal pump – Wafa Pomp, Q=2300m3/h.
- Installation of steel discharge pipeline DN500
Implementation date: September 2019 – July 2020
Investor: KGHM Polska Miedź S.A – Głogów smelter