Plant for the Production of Limestone and Dolomite Granules in Wojnowice.

24 January 2025
2 minutes of reading

We have successfully completed another implementation! It was a very interesting but also challenging project, and we feel great satisfaction from this cooperation. Thank you for your trust and we look forward to more joint projects in the future!

Project: Construction of a Plant for the production of lime and dolomite granules with additives.

Scope of work:

  • Delivery and installation of steel structures with a total weight of about 1,000 tons,
  • supply and installation of hoppers for dolomite (25m3), sulfur (10m3) and additives (10m3)
  • Supply and installation of a steel buffer tank (12m3),
  • Delivery and installation of steel silos for: sub-grain (2m3), finished product – 3 pcs (17m3),
  • Supply and installation of steel silos for: premix (20m3), dust (12m3),
  • Supply and installation of an outdoor steel silo for dolomite meal (249m3),
  • Supply and installation of steel chimneys for the mill and granulation system with diameters
  • comprehensive assembly of a technological line for milling and granulation of dolomite stone, including additives, including: ball mill prod. Cemtec, dryer prod. Binder, belt conveyors prod. Inocon and Schenk, screw conveyors prod. Inocon, sliding conveyors prod. Kemex. , bucket conveyors prod. Aumund and Nerak, bag filters prod. Scheuch, sifter prod. Allgaier , granulating discs prod. Agglotec, radial fans prod. Scheuch, mixer prod. Eirich, hot air generators prod. Tecflam, compressors prod. Atlas Copco, and many other minor associated elements.
  • Supply and installation of the following systems: dust removal, compressed air, fuel oil, low and medium pressure external gas, internal gas, process water, molasses heating and pneumatic transport.
  • Supply and installation of internal installations (water, sewage, central heating, ventilation, air conditioning, gas).
  • Trials and functional tests and commissioning of the process line.