Signing a contract with Mostostal Kraków S.A.
Subject of the contract: Construction of sanitary installations and roof drainage system of the Electrolytic Baths Hall.
Task scope:
- Supply and installation of a roof drainage system for the Electrolytic Baths Hall at the P-7 Department at the Głogów smelter. The total length of the installation about 3000 mb.
- execution of insulation of pipelines of drainage system
- Replacement of elements of the rainwater drainage network with the construction of new wells
Implementation date: March 2020 – August 2021
Investor: Mostostal Kraków S.A.
General Contractor: SPS INSCON Sp. z o.o.