Signing a contract with PLAST INSTAL SKB Sp. z o.o.

26 September 2021
1 minutes of reading

Subject of the contract: Installation works – “P-24 Replacement of carousel machine for stationary anode furnaces together with modernization of extraction and dust removal system Construction and installation works”.

Task scope:

– Underground installation of gravity flow piping from the cooling tower with diameters DN630, DN500 to the intake tank of the chilled water pumping station (pool)
– Underground installation of a gravity drain pipe system from the cooling tower with a diameter of DN200 to the intake tank of the chilled water pumping station (pool)
– Installation of gravity runoff piping from the carousel with diameters DN250, DN300, DN500, DN600
– Installation of a hydrophore unit in the hydrophore room located in the P-24 hall, along with piping systems supplying cooling water to the M-28 bottling machine for anode carousel casting, installation of piping from the discharge port of the hydrophore unit by pipeline to the bottling machine


Implementation date: September 2021 – December 2021
Investor: KGHM Polska Miedź S.A.
General Contractor: PLAST INSTAL SKB Sp. z o.o.