Signing of a contract with Przedsiębiorstwo Techniki Cieplnej “PIECOSERWIS”

30 September 2022
1 minutes of reading

Subject matter: Construction of steel structures for the heating chambers, as well as fabrication and installation of the gas, combustion air and cooling air systems as part of the task entitled. “Replacement of furnaces and exhaust extraction system of rotary dryers S1 and S2 in ZWR Rudna District”.

Task scope:
– Making 2 kpl. steel structure of the KGSO N=5MW heating chamber (NNG) of rotary dryers S1 and S2
– Making 2 kpl. prefabricated installation of gas, combustion air and cooling air of the KGSO N=5MW heating chamber (NNG)
– Installation of gas, combustion air and cooling air of the KGSO N=5MW (NNG) heating chamber of S and S2 dryers


Implementation date: September 2022 – January 2023
Ordering party: Przedsiębiorstwo Techniki Cieplnej “PIECOSERWIS”
General Contractor: SPS INSCON Sp. z o.o.