Subject of the contract: Construction of a deep well with the installation of a new chlorinator at the SUW in 2021/2022.

Task scope:
– Construction of a deep well with associated infrastructure and transmission pipeline
– Construction of a transformer station with the installation of complete equipment
– Construction of a raw water pipeline to the existing drinking water system from Orsk – installation of the system including a chamber
– Location along the raw water system of the electrical supply and control system with their introduction to the target facilities
– Construction of vent and drainage manholes along the raw water pipeline
– Connection of power supply and control from the transformer station to the OSR 15/1 splitter with the expansion of the electricity billing system


Implementation date: September 2021 – November 2022
Investor: KGHM Polska Miedź S.A. – Cedynia copper smelter in Orsk
General Contractor: SPS INSCON Sp. z o.o.